According to TechCrunch, Crusoe confirmed on November 6 that it sold its unfinished data center project in southeast Wyoming to Google. Google says it plans to invest $17 billion in its first data center in the state. The purchase price was not disclosed.

The $17 billion figure is Google's planned investment, not a disclosed payment to Crusoe. In its November 5 blog post, Google describes a long-term project in Laramie County. That company account is the primary record for the spending and energy plans.

TechCrunch says Google took over after concerns about the cost and schedule under Crusoe. Those concerns were reported by the outlet, not set out as agreed findings in Google's blog. Crusoe had planned the site with Tallgrass before the sale.

Google says it will cover the power it uses and the new infrastructure needed for its growth. It describes plans for fuel cells that use natural gas, with carbon capture and storage. Those are the company's plans, not evidence that the systems are already in use or that their promised results have been met.

Google also says the campus will use air cooling to limit water use. Its blog describes talks with local residents about taxes, jobs and the wider effects of data center growth. The company says it and its partners plan a community council.

Crusoe has not ended all its work with Google. TechCrunch reports that it is building another Google data center near Amarillo, Texas. The Wyoming sale therefore does not mean the firms have stopped doing business together.

What we know: Crusoe confirmed the sale, and Google announced its planned investment.
What we don't know: Only TechCrunch has reported this so far; NewsHabit hasn't seen independent confirmation.